This page allows you to specify the other preventive maintenance schedules that must be carried out. Tell me more.
Select the “Dependent PM(s)” link from the bottom of the “Edit PM Schedule” page.
The “Dependent PM” page appears.
The system displays the following fields:
PM |
The preventive maintenance schedule number for which dependent preventive maintenance schedules must be defined. |
The description of the schedule is displayed alongside. |
|
Zoom facility available |
|
PM On |
The maintainable object on which preventive maintenance must be carried out. The system displays “Equipment” or “Location”. |
Code |
The equipment or location on which preventive maintenance must be carried out. |
The description of the equipment or location is displayed alongside. |
|
Zoom facility available |
Enter the following fields in the “Calendar Based Dependent PM” multiline:
PM |
The preventive maintenance schedule that must be performed after the execution of the preventive maintenance schedule displayed in the “PM” field in the header on the lapse of the period specified in the “Due After” field in the multiline (Alphanumeric, 18). Ensure the following: |
|
|
|
|
This field cannot be modified. |
|
Help facility available |
|
Press <Enter>. The system retrieves the “Description”, “PM On” and “Code” fields in the multiline. |
The system displays the following fields in the multiline:
Desc. |
The description of the preventive maintenance schedule. |
PM On |
The maintainable object on which the preventive maintenance is carried out. The system displays “Equipment” or “Location”. |
Code |
The equipment or location on which preventive maintenance is carried out. |
Enter the following fields in the multiline:
Due After |
Enter the time interval after the execution of the primary preventive maintenance, this dependent preventive maintenance must be executed (Decimal). Data entry in this field is mandatory if you have specified a preventive maintenance schedule in the “PM” field in the multiline. Ensure that the time interval is not negative. |
Interval Unit |
Use the drop-down list box to specify the unit of the interval specified in the “Due After” field. The system provides the options: “Days”, “Weeks”, “Months” and “Years”. Do not leave this field blank, if you have specified a dependent preventive maintenance in the multiline. |
Note: Ensure that the “PM – Due After – Interval Unit” combination is unique to the multiline.
Remarks |
Any additional information about specifying the dependent preventive maintenance schedule (Alphanumeric, 255). |
Enter the following fields in the “Usage Based Dependent PM” multiline:
PM |
The preventive maintenance schedule that must be performed after the execution of the preventive maintenance schedule displayed in the “PM” field in the header on the lapse of the parameter value specified in the “Due After” field in the multiline (Alphanumeric, 18). Ensure the following: |
|
|
|
|
This field cannot be modified. |
|
Help facility available |
|
Press <Enter>. The system retrieves the “Description”, “PM On” and “Code” fields in the multiline. |
|
The system displays the following fields in the multiline. The system displays this field only when you click the “Edit” pushbutton. |
|
Desc. |
The description of the preventive maintenance schedule. |
PM On |
The maintainable object on which the preventive maintenance is carried out. The system displays “Equipment” or “Location”. |
Code |
The equipment or location on which preventive maintenance is carried out. |
Enter the following field in the “Usage Based Dependent PM(S)” multiline:
Parameter |
The parameter value based on which the dependent preventive maintenance is carried out (Alphanumeric, 30). Data entry in this field is mandatory if you have specified a dependent parameter in the “PM” field in the multiline. Ensure the following: |
|
|
|
|
|
|
Help facility available |
|
Press <Enter>. The system retrieves the “Interval Unit” field in the multiline. |
|
Due After |
Enter the incremental value of the parameter after the execution of the primary preventive maintenance, this preventive maintenance must be performed (Decimal). |
Data entry in this field is mandatory if you have specified a dependent preventive maintenance in the “PM” field in the “Usage Based Dependent PM(S)” multiline. |
|
Ensure that the value entered in this field is not negative. |
|
If you leave this field blank, the system considers the incremental parameter value as “0”. |
Note: Ensure that the “PM – Parameter – Due After” combination is unique to the multiline.
The system displays the following field in the multiline:
Interval Unit |
The unit of measurement of the parameter. |
Enter the following field:
Remarks |
Any additional information about defining the usage-based dependent preventive maintenance for the primary preventive maintenance (Alphanumeric, 255). |
Click the “Edit” pushbutton to save the details of the dependent preventive maintenance schedules.
Note: The system saves the details of the dependent preventive maintenance schedules and refreshes the “Description”, “PM On” and “Code” fields in both the multilines and the “Interval Unit” in the “Usage Based Dependent PM” multiline.
The system displays the following fields in the “Record Statistics” group box:
Created By |
The login ID of the user who created the preventive maintenance schedule. |
Created Date |
The date and time at which the preventive maintenance schedule was created. |
Last Modified By |
The login ID of the user who last modified the preventive maintenance schedule. |
Last Modified Date |
The date and time at which the preventive maintenance was last modified. |
Specifying dependent preventive maintenance schedules – An overview
This page allows you to specify the other preventive maintenance schedules that must be carried out if this preventive maintenance schedule is performed. You can define calendar-based dependent schedules or usage-based schedules. The preventive maintenance schedule for which dependent schedules are defined is referred to as the primary schedule.
You can define calendar-based dependent schedules by specifying the following details:
The dependent preventive maintenance schedule that must be carried out.
The period after the performance of the primary preventive maintenance schedule, during which the dependent schedule must be performed.
The unit of interval of the period.
Any additional information regarding the dependent schedule.
You can define usage-based dependent schedules by specifying the following details:
The dependent preventive maintenance schedule that must be carried out.
The parameter value of the primary preventive maintenance schedule, based on which the dependent schedule must be carried out.
Any additional information about the dependent schedule.
“Create PM Schedule”
Specify the dependent preventive maintenance schedules
Specify the dependent preventive maintenance schedules
You can specify the dependent preventive maintenance schedules that must be carried out on the execution of the preventive maintenance.
Enter the preventive maintenance schedules that must be performed after the lapse of a specified period in the “Calendar Based Dependent PM (S)” multiline.
Enter the preventive maintenance schedules that must be performed based on a parameter value in the “Usage Based Dependent PM (S)” multiline.