This page allows you to view the spare parts that are required for carrying out preventive maintenance during the forecast period. Tell me more.
Select the “Spare Parts Requirements” link from the bottom of the main page.
The “Spare Parts Requirement” page appears.
Enter the following field if you wish to view the spare parts requirements for a forecast other than the forecast selected in the previous page.
Forecast Review No. |
The number of the forecast for which spare parts requirements must be viewed (Alphanumeric, 18). |
Press <Enter>. The description of the forecast review is displayed alongside. |
|
Zoom facility available |
|
The system displays the following fields: |
|
From Forecast Date |
The starting date of the forecast. |
To Forecast Date |
The ending date of the forecast. |
The system displays the following fields in the “Spare Part Reqt.” multiline: |
|
Date |
The date on which the spare part is required. |
Item |
The item number of the standard spare part that is required. |
Variant |
The variant of the item. |
Desc. |
The description of the spare part. |
Qty. |
The number of spare parts required. |
UOM |
The unit of measurement of the spare part. |
Warehouse |
The warehouse from which the spare part is procured. |
Select atleast one row from the spare parts multiline.
Click “Get Stock Availability” pushbutton to retrieve the stock details of the item.
The system displays the following fields in the multiline:
Item |
The item number of the standard spare part. |
Variant |
The variant of the item. |
Desc |
The description of the spare part. |
UOM |
The unit of measurement of the spare part. |
Warehouse |
The warehouse from which the spare part is procured. |
Item Status |
The status of the item. |
Req. Qty. |
The number of spare parts required. |
Available Qty. |
The number of spare parts available in the warehouse. |
This page allows you to view the spare parts that are required for carrying out preventive maintenance during the forecast period. You can view the spare parts requirements for a forecast review that is selected from the previous page. You can also directly enter a forecast review in this page and view the details of the spare parts that are required for the preventive maintenance schedules during the forecast period. The system displays the following details of the spare parts requirements:
The item and the variant of the standard spare parts that is required
The description of the spare part
The number of spare parts required for carrying out the preventive maintenance
The unit of measurement and the warehouse from which the spare part must be procured.