You can specify a staggered schedule for the service requirements of a work order. Tell me more
Select the “Give Staggered Schedule” link from the bottom of the “Schedule WO Services” page.
The “WO Service Staggered Schedule” page appears.
The system displays the following fields:
|
WO No. |
The work order for which the staggered schedule must be defined. |
|
Date |
The date on which the work order is created. |
|
Status |
The status of the work order. |
|
Desc. |
The description of the work order. |
|
Zoom facility available |
|
|
WO On |
The maintainable object on which the work order is raised. The system displays either “Equipment” or “Location”. |
|
Code |
The equipment or location for which the work order is raised. |
|
WO Sch. Start Date |
The date on which the work order is scheduled to start. |
|
WO Sch. Compl. Date |
The date on which the work order is scheduled to complete. |
Enter the following fields in the “Service Details” group box:
|
Line No |
Use the drop-down list box to select the line number for which you wish specify the staggered schedule. The system lists all the line numbers that identifies a unique service requirement of a work order and for which the schedule is specified as “Staggered”. |
The system displays the following fields:
|
Service Code |
The service required for carrying out the work order. |
|
Service Variant |
The variant of the service code. |
|
Service Desc. |
The description of the service. |
|
Zoom facility available |
|
|
UOM |
The unit of measurement of the service. |
|
Total Est. Qty. |
The quantity of service that is estimated for carrying out the service. |
Enter the following fields in the “Sch.” multiline:
|
Date |
The date on which the service is required (Date Format). Ensure that the date is unique in the multiline. |
|
Sch. Qty. |
The scheduled quantity of service that is required (Decimal). The quantity cannot be negative. . Ensure that the date entered is not earlier than the date displayed in the “WO Sch. Start Date” field. |
Check the box in the “Select” column of the multiline to select the multiline row for deletion.
Click the Delete icon in the tool bar above the multiline to delete the selected rows.
Click the “Save” pushbutton to save the schedules dates.
The system displays the following details in the “Record Statistics” group box:
|
Created By |
The login ID of the user who created the list. |
|
Created Date |
The date and time at which the list was created. |
|
Last Modified By |
The login ID of the user who last modified the list. |
|
Last Modified Date |
The date and time at which the list was last modified. |
Specify the dates for a staggered schedule
Specify the dates for a staggered schedule
You can specify the dates on which service is required for a staggered schedule.
Enter the dates the quantity of service required as on that date in the “Date” and “Sch. Quantity” fields in the “Schedule” multiline.
Click the “Save” pushbutton.
WO Service Staggered Schedule – An overview
You can specify a staggered schedule for the service requirements of a work order. You can select the line number for which you wish to specify the staggered schedule and specify the staggered schedule in the mulitline.
You can specify the staggered schedule by entering the dates and the quantity of service that is required as on that date. The staggered schedule can be defined only for a service for which the schedule type has been set to “Staggered” in the “Schedule WO Services” page.