This activity allows you to view the other resources that are specified for the task selected in the previous page. Tell me more.

The “View Other Resource Requirement” page appears.

Task

The task for which you wish to view the other resource details (Alphanumeric, 30).

 

Press <Enter>. The system retrieves the details of the resources that are specified to the task. The textual description of the task is displayed alongside

 

Zoom facility available

 

The system displays the following fields in the multiline:

Other Res. Code

The resource assigned to the task.

Desc.

The textual description of the other resource.

Duration In Hrs.

The number of hours for which the resource is required.

Qty. (Nos.)

The number of resources required for the completion of the task.

Res. Cost / Hr.

The unit cost per hour of the resource.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Viewing other resource requirements for the task – An overview

View Tasks - A summary of the activity

This activity allows you to view the other resources that are specified for the task selected in the previous page. You can also directly enter a task other than the task selected in the previous page and view the other resources that are specified for it.

The details of the resources such as the resource description, the period for which the resource is required, the number of resources required and the unit cost of the resource per hour of the resource are displayed.