Help on Run

Unified Glossary

Basics of using a Ramco iEnterprise Series 4.0 Web Page

Using Online Help

You can select a run number from this page. You can select a run number by carrying out a search based on the run number, the planning group and the dates for which the MRP was run. Based on the search criteria entered, the system retrieves the run numbers in the multiline.

The “Help on Run” page appears.

Run No.

The run number which you wish to retrieve (Alphanumeric, 18). You can enter the run number in full or specify it partially. The system retrieves all run number similar to the run number entered here.

Planning Group

The planning group for which the MRP was run (Alphanumeric, 30). You can enter the planning group in full or specify it partially. The system retrieves all run numbers of the MRPs that were run for similar planning groups.

From

The date starting from which the MRP was run (Date Format).

To

The date till  which the MRP was run (Date Format). Ensure that the date entered in this field is later than the date entered in the “From” field.

The system retrieves the following fields in the “Search Results” multiline:

Run No.

The run number retrieved by the system.

Date

The date on which the MRP was run.

Status

The status of the MRP.

Planning Group

The planning group for which the MRP was run.