View Flexible Budget

Component Overview

Glossary

Basics of using Ramco Enterprise series web page

This activity allows you to select the flexible budget you want to view. You can use the search criteria to access and view all the relevant details of the flexible budget.

The "Select Flexible Budget " page appears.

Budget No. From

The starting number in the range of numbers identifying the budget from which you want the details to be fetched in the multiline (Alphanumeric, 10).

To

The ending number in the range of numbers till which you want the details to be fetched (Alphanumeric, 10).

Version No.

Use the drop-down list box to select from “latest” or “All.” The system displays “All” as default on launch of the page.

Start Date

Use the drop-down list box to select from the available start dates in the range of dates from which you want to fetch budgets for viewing. The system displays the earliest Start Date as default on launch of the page.

End Date

Use the drop-down list box to select from the available end dates of periods. The system displays the latest End Date as default on launch of the page.

Cost Center From

The starting name in the range of names of the cost center from which you want the budget details to be fetched (Alphanumeric, 32).

To

The ending name in the range of cost center names till which you want the budget details to be fetched  (Alphanumeric, 32).

Flex Variance Option

Use the drop-down list box to select from “Flat” or “Percentage.”  The system displays “Flat” as default on launch of the page.

Filter Basis

Use the drop-down list box to select from “Quantity,” “Value” or “Both.”

Filter Option

Use the drop-down list box to select the required relational operator from “<,” “<=,” “=,” “>” or “>=.”

Percentage / Value

Enter the percentage or variance (Integer, 20)

The system displays the following:

Budget No.

The number identifying the budget.

Version No.

The version number identifying the budget.

Accounting Period

The accounting period of the budget.

Cost Center / Unit

The cost center / unit linked to the budget.

Basic Activity Element

The activity element cost of the budget.

Budget Qty.

The quantity according to the budget.

Flexed Qty.

The flexed quantity allowed.

Report Type

Use the drop-down list box to select from “Flexible Budget Report” or “Flexible Budget Listing.” The system displays 'Flexible Budget Report' as default on search.