Skill Requirement

Set Option - A summary of the activity

Unified Glossary

Basics of using a Ramco iEnterprise Series 4.0 Web Page

Using Online Help

This activity allows you to review the details of a forecast that is already done. You can select the forecast to be reviewed in the “Select PM Forecast Review” page. You can review the forecast in the “PM Forecast Review” page. You can also view the spare parts that are required to carry out preventive maintenance during the forecast period in the Spare Parts Requirements page.

The “Skill Requirement” page appears.

Forecast Review No.

The forecast number for which the skill details are viewed.

The system displays the following details in the header:

Desc.

The description of the forecast number. (Display Only)

From Forecast Date

The date range from which the forecast is done.

To Forecast Date

The date range until which the forecast is done.

The system displays the following details in the multiline:

Date

The date on which the skill is mapped to the preventive maintenance.

Skill

The name of the skill.

Desc.

The detailed description of the skill.

Qty. (Nos.)

The number of quantities required for the skill.

Duration (Hrs.)

The total duration of hours the skill is required.