Task List
This tab allows you to map existing tasks to a project. Task details entered are applicable for the selected project only. New tasks can also be created. The Maintain Task master is updated. Subsequent modifications of newly created tasks are not updated in the "Maintain Task" masters.
Select the Task List tab.
The Task List tab appears.
Enter the following details in the "Task List" multiline:
Task Code |
The unique code identifying the task. On press of the Enter key the system retrieves the task description, task group, output quantity, output UOM, effort, time UOM from the "Maintain Task" and displays it. |
|
Help facility available. |
Task Desc. |
The descriptive information about the task. |
Task Group |
Use the drop-down list box to select the task group. The values for this task get populated. |
Effort |
The total effort spent on the task to execute the output quantity specified for the task. |
Time UOM |
Use the drop-down list box to select the time UOM. User can select Days or Hours |
Output Qty. |
The total output quantity of the task. |
Output UOM |
The UOM of the output. |
|
Help facility available. |
Summary Activity |
Use the drop-down list box to select the summary activity. The values "Yes" and "No" get populated. The system displays the value "Yes" on launch of the page. Note: If a task is created with summary activity as "Yes" then RM and resource details should not be entered. |
Click the "Maintain" pushbutton to save the entered task list details.
Note: Changes made to the output quantity in a parent task / change in material requirements / new material added to a parent task in Project BOM, will be carried forward to the complementary task of the parent in all the work areas where the parent task has been mapped for the project tasks in a cascading effect.