Setup Action Messages Global Parameters
This page allows you to setup action messages or exceptions. Tell me more
Select the “Setup Action Messages Global Parameters” link under the “Supply Chain Model“ business component.
The “Setup Action Messages Global Parameters” page appears.
Enter the following:
Plant |
Use the drop-down list box to select the valid plants. The system retrieves all warehouse Organization Unit in the Business Unit for which the user has at least “View” access permission. The system displays “Login Plant” by default on launch of this page. If action messages are setup at plant level, then this field is populated with all the warehouse Organization Unit for the login Business Unit. |
The system displays the following:
Business Unit |
The business unit for which the setup action messages is raised. If action messages are setup at Business Unit level, then the system will not load the plant field details. |
Click the “Get” pushbutton to retrieve the plant and business unit details.
The system retrieves all the action messages, action type, parameter listed below and their values (if available). The repeated action message indicates dependency i.e. it has to be selected together for processing. If the parameter values are already defined, then the system retrieves the stored values. Otherwise the system retrieves only the list of action messages and the parameters.
Enter the following:
Action Message Horizon |
The horizon limit to the extent the parameter value is restricted. You can enter action message horizon as highest as the MRP item’s planning horizon or this field is displayed based on login plant and business unit. The action message horizon should be integer and should be greater than zero. |
Enter the following in the “Action Type Deployment” group box:
Time Triggers |
Select the checkbox to indicate the time trigger based exceptions or action messages deployed. When this option is selected, the system suggests to accept/firm up/release the orders or converts purchase requisitions to purchase orders. Hence, the acceptance horizon, firm up horizon, days to be considered for releasing orders/purchase orders and the limit of generated order number will be defined. The system leaves the box “Unchecked” by default on launch of the page. |
Reschedules |
Select the checkbox to indicate the reschedule-based exceptions or action messages deployed. When this option is selected, the orders that are rescheduled, to be amended or cancelled are identified and the no of days are defined based on which past due work orders, past due sale orders, past due forecast and past due scheduled receipts are suggested. The system leaves the box “Unchecked” by default on launch of the page. |
Matl. Shortages |
Select the checkbox to indicate the material shortage related exceptions or action messages deployed. When this option is selected, the sale orders and the work orders that have material shortages are identified. The system leaves the box “Unchecked” by default on launch of the page. |
Pending Transactions |
Select the checkbox to indicate the pending transaction based exceptions or action messages deployed. When this option is selected, the no of days pending for “Goods Inward”, “Inventory Receipt” or “EC” pending for approval, request for estimate is identified. The system leaves the box “Unchecked” by default on launch of the page. |
Capacity |
Select the checkbox to indicate the capacity related exceptions or action messages deployed. When this option is selected, the resource under utilized/over utilized along with its over load %/under load % are identified. The system leaves the box “Unchecked” by default on launch of the page. |
Item Code |
Select the checkbox to indicate the item related exceptions or action messages deployed. When this option is selected, the item in shortage or in excess,the item having no demand for last “No of Days”, the stock that has reached below “Safety Stock”, the scrap qty that has gone beyond “Quantity” or the expired lot for item, Items with no activity or high inward rejection are identified. The system leaves the box “Unchecked” by default on launch of the page. |
Data Modeling |
Select the checkbox to indicate the data modeling related exceptions or action messages deployed. When this option is selected, the item without warehouse planning parameters, item without product structure/process plan, items without PS-PP link, and resource without cost details are identified. The system leaves the box “Unchecked” by default on launch of the page. |
Click the “Default Details” pushbutton to retrieve the default values set for the action message type.
All the action messages are grouped as action types time triggers, re-schedules, matl shortages, pending transactions, capacity, item and data modeling. If specific action type is selected or not selected, all action messages for the action types are set to "Yes" or "No" respectively in Deploy Combo.
The system displays the following in the “Action Message” multiline:
Action Messages |
The action messages or exceptions to be associated which will be raised by the system if certain conditions are not satisfied based on the parameter and parameter values. The field displays the messages based on the action message type chosen. The action messages to be deployed are |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Action Type |
The type of action messages. The system displays “Pending Transactions”, “Data Modeling”, “Capacity”, “Item”, “Matl Shortages”, “Re-Schedule” or “Time Triggers”. |
Enter the following in the “Action Message” multiline:
Deploy |
Use the drop-down list box to indicate whether the action messages are to be deployed or not. You can select from “Yes” or “No”. The system displays “No” by default on launch of the page. |
The system displays the following in the “Action Message” multiline:
Parameter |
The parameter defined for the action message. The system raises the exceptions or action messages based on this parameter. |
Enter the following in the “Action Message” multiline:
Value |
The value of the parameter for which system looks for conditions. If the Deploy field is set to "Yes", then all percentage parameter values should be within “0-100%”. For example, if the safety stock should not go below 10, then the value will be set to “10”. If Deploy field is set as "Yes", then all “No of Days” parameter values should be greater than or equal to zero, all “Status” parameter values should be “E”, “F” or “G”, all “Qty” parameter values should be greater than or equal to zero. And also all the data modeling action messages should not have any values. |
Check the box in the “Select” column of the multiline to select the action messages for setting up its details.
Click the “Setup Action” pushbutton to setup action messages through global parameters.
The system saves all action messages along with parameters and values for the Business Unit and the Plant based on action message setup level parameter. Action message horizon and all messages with validated values are also saved by the system.
The system updates the login ID of the user to the “Edited By” and the system date to the “Edited Date” field.
To proceed, carry out the following
Select the “Setup Action Messages – Item Level” link at the bottom of the page to setup action messages at item level.
Select the “Setup Action Messages – Resource Level” link at the bottom of the page to setup action messages at resource level.
The system displays the following:
Created By
|
The login ID of the user who created the setup action messages through global parameters. |
Created Date |
The date on which the setup action messages through global parameters was created. |
Edited By |
The login ID of the user who modified the setup action messages through global parameters. |
Edited Date |
The date on which the setup action messages through global parameters was modified. |
Setup Action Messages Global Parameters - An overview
The action messages are user-defined messages that can be defined globally or for a particular item/item group or for a particular resource or resource type. In this screen, you can define action messages using the global parameters. You can set the action messages either at location (plant) level or company (business unit) levels. You can select from various types of action like item related exceptions, capacity related messages, data modeling, transactions that are pending, orders to be rescheduled, shortage of materials and time triggers based on which the action messages are displayed in the multiline. If a specific action type is selected and defaulted, then all the action messages of that type are set for deployment.
The action messages suggest the corrective action to be taken for the present or future item/resource problem. These messages are generated during MRP planning. You can specify the parameter value for each of the parameter set. Hence, the action is taken based on the parameter along with its value defined in the multiline. You can set more than one parameter to a single action message. In such a case, you need to deploy both the messages together. For example, consider an action message set with two parameters and the way it is deployed. The action-planning horizon is set as 5 days.
Action Messages |
Action Type |
Deploy |
Parameter |
Parameter Value |
Resource under utilization |
Capacity |
Yes |
Utilization % |
90 |
Resource under utilization |
Capacity |
Yes |
No of Days |
7 |
In the above table, the system raises the action messages whenever the resource utilization is under 90 % for a period of 7 days. This limit should not exceed the action message horizon defined. If the limit specified in the parameter value exceeds the horizon limit, then the parameter value is replaced with the horizon value. The above condition is checked for all action messages whose parameter is set to no of days.