View Delivery Details

Unified Glossary

Basics of using Ramco Enterprise series web page

This page allows you to View the delivery details of the items received from the supplier. Tell me more

The “View Delivery Details” page appears                

The system displays the following in the header

Status

The status of the GR

The system displays the following information in the “Receipt Details” group box

Receipt No.

The unique code identifying the GR

Date

The creation date of the GR

Type

The type of receipt document. The different types are General, Consignment, Capital, Conversion, Service, Activity, Normal and Certificate on Delivery.

Ref.  Doc.

The type of reference document referred by the receipt document. The different types of reference document are Purchase Order, Purchase RS, Subcontract Order, Subcontract RS, Goods Return Note and Sale Order.

Ref.  Doc.  No.

The unique code identifying the reference document

Date

The creation date of the reference document

Supplier Code

The unique code identifying the supplier or customer

Name

The name of the supplier or customer

Freeze Receipt Date

The date on which the Receipt document is “Frozen” for further processing

Level

Use the drop-down list box to select the level at which the delivery details needs to be viewed

Line No.

Use the drop-down list box to select the line number of the item in the GR. The drop-down lists all the line numbers in the receipt along with blank value

The system displays the following information in the “Item Details” group box

Line Status

The current status of the line item

Item Code

The unique code identifying the Item

Variant Code

The variant of the item code

Desc.

The description of the item

Qty.

The number of units of the line item received

UOM

The unit of measurement of the item

The system displays the following information “Delivery Details” Multiline

Receipt Line No.

The line number of the item in the GR

Expected Dely Date

The date on which the items are expected to be delivered

Actual Receipt Date

The date on which the items are delivered

Delay in Days

The number of days delayed to deliver the item

 

Delay in Days = Actual Receipt Date – Expected Delivery Date

Delay Attributed To

The group responsible for the delay in delivering the goods. The options available in the list box are Material Supplier, Company, , Any Other user-defined value.

Days

The number of days delayed by the value selected in the “Delay Attributed To” field

Order Quantity

The number of units of the item ordered

Expected Qty.

The number of units of the item expected to be delivered

Received Qty.

The number of units of the item received

Shortage Qty.

The number of units which is short of the expected quantity

 

Shortage Qty = Expected Qty – Received Qty

Shortage Attributed To

The group responsible for the shortage of items. The options available in the list box are Material Supplier, Company, , Any Other user-defined value

Quantity

The quantity of items short due to the value selected in the “Shortage attribute To”  field.

Line Status

The status of line item is displayed

To proceed carry out the following:

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

View Delivery Details – An Overview

The goods delivered to the buyer could have a number of delivery flaws such as the number of units delivered might be short of the expected number of units from the supplier or the items might have not reached the buyer on time. This page allows you to view the delivery flaws.

This page displays all the receipt details like the receipt number, receipt date, the type of the receipt document. This page also displays the reference document details like the type reference document, the reference document number, and the date of creation of the reference document.

On giving the line number the item details are displayed such as the item code, the variant of the item, textual description of the item, the quantity of item received, the unit of measurement of the item received.

In the multiline you can view the shortage in quantity or the delay in days attributed to the material supplier or the company or any other agency.