Viewing the details of cost incurred on the plan
This page allows you to view the cost details of the plan. Tell me more.
Select the “View Cost Details” link from the bottom of the main page.
The “View Cost Details” page appears.
The system displays the following fields:
Plan No. |
The number of the plan for which cost details must be viewed. |
The description of the plan is displayed alongside. | |
|
Zoom facility available |
Sch. Start Date |
The date on which the plan is scheduled to start. |
Sch. Compl. Date |
The date on which the plan is scheduled to end. |
Est. Duration (Hrs.) |
The number of hours required for carrying out the plan. |
Est. Cost |
The estimated cost of carrying out the plan. |
Spent So Far |
The amount that is already spent on carrying out the plan. |
% Spent |
The percentage of money spent on carrying out the plan. |
The system displays the following fields in the “Cost Details” multiline:
Code |
The equipment or location for which cost is viewed for carrying out the plan. |
Maintenance On |
The maintainable object for which the plan was created. The system displays “Equipment” or “Location”. |
Desc. |
The description of the equipment or location. |
Work Sch. From |
The date on which the work on the plan is scheduled to start for the equipment or location. |
To |
The date until which the work on the plan is scheduled for the equipment or location. |
No. Of WOs |
The number of work orders that are raised for the equipment or location as a part of the plan. |
Est. Cost |
The estimated cost of carrying out the work orders on the equipment or location. |
Spent So Far |
The amount that is spent so far on the work orders. |
% Spent |
The percentage of money with respect to the estimated cost that is spent on the work orders. |
The system displays the following fields in the “Record Statistics” group box:
Created By |
The login ID of the user who created the plan. |
Created Date |
The date and time at which the plan was created. |
Last Modified By |
The login ID of the user who last modified the plan. |
Last Modified Date |
The date and time at which the plan was last modified. |
To proceed, carry out the following
Select the “View Plan Progress” link at the bottom of the page to view the progress made on the plan.
Select the “View Part Availability” link at the bottom of the page to view the details of spare parts that are required for carrying out the plan.
Select the “View Material Planning” link at the bottom of the page to view the details of material that is required for carrying out the plan.
Viewing the details of cost incurred on the plan – An overview
This page allows you to view the cost details of the plan. The system displays the details of the cost incurred on carrying out the activities on the equipment or location as a part of the plan. Details of the cost such as the estimated cost of carrying out the plan, the costs incurred till date on the plan and the percentage of cost spent is displayed.