Edit Work Order Process Plan

Activity overview

Unified Glossary

Basics of using Ramco Enterprise series web page

Using online help

This page allows you to modify the process plan created for a work order. You can edit the process plan details by entering the work order no or by retrieving it using the help facility provided. On retrieving the work order no, the system retrieves all the details of the work order to the header. You can also view all the activities that are reported with capacity problems in the multiline.

You can modify the details of the activity of the process plan depending on the requirements of the work order. New activities/resources can be added. Existing activities along with the sub-activity times, the overlap percentage or the buffer times can be modified. You can modify only those activities that have not been started. The main resource of the activity can also be changed. You can edit the capacity requirements of the resources. You can also delete the activities that have not been started. The activities/resources to be deleted are selected in the multiline and deleted. Help screen is provided to search and display the activity details. Upon modifying or deleting the necessary details, you can update the changes made to the work order. 

The “Edit Work Order Process Plan” page appears.

Work Order No.

The number identifying the work order for which the process plan has to be modified. Mandatory. Work Order should be defined in the system for the Business Unit.

 

Help facility available.

If “View Capacity Shortages” is enabled, only those activities that have capacity problem are displayed in the multiline.

The system displays the following:

Order Qty.

The planned quantity of the work order. This is the sum of the receipt quantity and expected scrap quantity.

Order Status

The status of the work order. It can be “Requested”, “Accepted”, “Firmed” or “Released”.

Item code

The code identifying the item based on which the work order process plan has to be modified.

Variant Code

The code identifying the variant of the item code for which the work order process plan has to be modified.

Desc.

The description of the item/item variant.

 

Zoom facility available.

Order Start Date

The start date of the work order.

Order Due Date

The due date of the work order.

View Capacity Shortages

Select the check box to get only those activities or PP sequences, which have capacity shortage. The system leaves the box "Checked" by default on launch of the page. If enabled, only those Items/PP Sequences that have capacity problem are displayed in the “Process Plan Details” multiline.

PP Seq.

The position number identifying a position in the work order process plan. Mandatory. This field cannot be modified for an existing activity. The PP Seq specified should be unique for the Work Order Process Plan.

Note: If new rows are inserted in the multiline, then the PP Seq should have been entered.

Activity Code

The code identifying the activity that is required in the work order process plan. Mandatory. The activity should be valid for the Business Unit for which the work order is created and should be in “Active” status. The activity codes are retrieved from activity master.

 

Help facility available.

Short Desc.

The short description of the activity. Mandatory.

The system displays the following in the “Process Plan Details” multiline:

Start Date / Time

The planned start date and time of the activity. The system displays "Blank" by default on launch of the page.

End Date / Time

The planned completion date and time of the activity. The system displays "Blank" by default on launch of the page.

Activity Duration

The duration of the activity. This is expressed as the sum of the three components, which are time setup, time per., and time batch of an activity, for each Activity Code and PP Seq combination.

Duration Expended

 The elapsed time from the start of the activity to end. The system displays "Blank" by default on launch of the page.

Problem

The problems associated to the work order. It can be “No Problem”, “Material Problem”, “Capacity Problem”, “Matl & Cap. Problem”, “Engineering Change Problem”, “Order in Past date”, “Other Problems” or “Blank record”.

Run Timetype

The time duration required for the actual processing of the work order item. Mandatory. If specified, it should be greater than zero. 

Setup Timetype

The time duration required for the setup sub-activity. Mandatory. If specified, it should be greater than zero.

Batch Timetype

The time duration required for the batch sub-activity. Mandatory. If specified, it should be greater than zero.

The system displays the following in the “Process Plan Details” multiline:

Time UOM

The unit of measure used for specifying the time.

Transfer Lot Size

The quantity that can be moved in batches/lots after completion. Activity need not be complete, but once the specified quantities are completed in the activity, they can be moved to the next activity. The system displays “Zero” by default on launch of the page. If Transfer Lot Size has been entered, then it should be greater than or equal to zero.

Overlap %

The percentage, by which two successive activities overlap, if overlapping has been planned. The system displays "Zero" by default on launch of the page.

Note: Only one of overlap% or transfer lot size should have been entered.

Resource No.

The number identifying a resource required during the activity selected. Mandatory.

Note: If the Resource is selected in the multiline, it should exist for the Business Unit of the work order and should be in “Active” status.

Inspection Required

Indicates whether the activity requires inspection or not in order to plan the materials. The combo is loaded with “No” and “Yes”, The system displays “No” by default on launch of the page.

Checklist Mandatory

Indicates whether checklist based inspection for each activity has to be enabled or not while processing the work order process plan. The combo is loaded with “No” and “Yes”. The system displays “No” by default on launch of the page.

The system displays the following in the “Process Plan Details” multiline:

Subcontract

Indicates the activity being sub contracted to vendors/suppliers. If Sub Contract is set as 'Yes', then Supplier code has to be specified.

Supplier

The code identifying the supplier for the sub contracted activity. If supplier code is entered, then the supplier code should be active and should exist for the Business Unit.

Queue Time

The start time buffer that is to be given at the beginning of an activity, which uses this resource. If the queue time is specified for the selected row, queue time should be greater than or equal to zero.

Wait Time

The time buffer that is to be given at the end of an activity, which uses the resource being defined. If wait time is specified for the selected row, wait time should be greater than or equal to zero.

Transport Time

The time required for the job on this resource to move to the next resource in the shop. If transport time is specified for the selected row, wait time should be greater than or equal to zero.

The system displays the following in the “Process Plan Details” multiline:

Time UOM

The unit of measure used for specifying the time.

Run Cap Units

The capacity of the resource that is required for the actual processing of the work order item.

Note: If Run Cap Units for the resource has been entered and if the resource is a discrete resource, then the value to this field should be a whole number.  If activity Run Time has been entered for the selected row in the multiline, then the Run Capacity Units for the primary main resource has to be entered.

For the selected rows in the multiline, if secondary resources are specified and Run Time is equal to zero or not specified then the Run Cap Units should not be greater than zero.

Setup Cap Units

The capacity of the resource that is required during the setup sub-activity. Mandatory.

Note: If Setup Cap Units for the resource has been entered and if the resource is a discrete resource, then the value to this field should be a whole number. If activity Setup Time has been entered for the selected row in the multiline, then the Setup Capacity Units for the primary main resource has to be entered.

For the selected rows in the multiline, if secondary resources are specified and Setup Time is equal to zero or not specified then the Setup Cap Units should not be greater than zero.

Batch Cap Units

The capacity of the resource that is required during the batch sub-activity.

Note: If Batch Cap Units for the resource has been entered and if the resource is a discrete resource, then the value to this field should be a whole number. If activity Batch Time has been entered for the selected row in the multiline, then the Batch Capacity Units for the primary main resource has to be entered.

For the selected rows in the multiline, if secondary resources are specified and Batch Time is equal to zero or not specified then the Batch Cap Units should not be greater than zero.

No. Of Activity Cards

The number of job tickets to be printed for the activity when the work order is released.

Yield %

The percentage that is acceptable during reporting of the output item of the activity. Mandatory. If the quantity reported for the output item is less than the percentage specified here, the system gives an error message.

The system displays the following in the “Process plan” multiline:

Costing Reqd.

Indicates whether the process plan is used for costing purpose.

Costing Basis

Indicates whether costing is based on standard time or on actual reported time.  

Prodn. Reqd.

Indicates whether the activity is used for production purpose.

Lot No. Gen.

The lot number is generated at this activity only if the item is Lot No Controlled.

Serial No. Gen.

The serial numbers are generated at this activity only if the item is Serial No Controlled

Field1

The remark or comment specified by the user.

Field2

The remark or comment specified by the user.

Field3

The remark or comment specified by the user.

The Work Order No should be available in the system for the Business Unit of the Login Organization Unit. The system ensures that at least one input sequence should exist for the work order. The selected rows in the multiline cannot be modified, if duration expended is greater than zero or activity status is started. If the status of the order is less than or equal to “Requested” status, then the user should have at least “Modify” access permission to the material planner defined in the Control Unit. If the status of the order is greater than or equal to “Accepted” status, then the user should have at least “Modify” access permission to the production controller defined in the Control Unit.

The system does not insert an activity as the last activity if the previous activity with Production Reqd has been started. If only the Activity Code has been entered in the multiline, the system retrieves the Queue Time, Wait Time and Transport Time of the activity based on the primary resource for the activity. Work order in “Batch” mode cannot be modified.

For the selected row in the multiline that is marked for modification or deletion, PP Seq should be valid for the work order. The specific activity that is being modified, or deleted should not have been started. If rows are marked for deletion, PP Seq should not be associated to any PS Seq of the work order. If the selected PP Seq is deleted, then there should not be any activity with higher PP Seq that has already been started.

The login user ID and the system date are updated in the “Created By”, “Created Date”, “Edited By” and “Edited Date” fields.

The system displays the following:

Created By

The login user ID of the person who has created the work order process plan details.

Created Date

The date on which the work order process plan details was created.

Edited By

The login user ID of the person who has edited the work order process plan details.

Edited Date

The date on which the work order process plan details was edited.

To proceed, carry out the following