Create SC Release Slip

Unified Glossary

Basics of using a Ramco Enterprise series webpage

Using online help

This page allows you to create an SCRS based on the selected BSCO. Tell me more

The “Create SC Release Slip” page appears

The system displays the following in the header

Status

The status of the SCRS

 

SC Release Slip No.

The unique code identifying the subcontract release slip. (Alphanumeric, 18) Mandatory. This number is automatically generated and displayed by The system at the time of creating the, based on the numbering type selected in this page. The number should be entered if the “Numbering series” is “Manual”

Note: The “Blanket SCO NO” should not be blank if the “Numbering Series” is set to “Manual”

The “SC Release Slip No.” is auto generated if the “Numbering Series” is anything other than “Manual” with the prefix or suffix selected in the “Numbering Series” on the click of “Create” or “Create and Approve” pushbutton 

The system displays the following information “SC Release Slip Details” group box

Amendment No.

A unique code identifying the amendment done to the subcontract release slip. Amendment is normally done after the approval of the document

Numbering Series

Use the drop-down list box to select the numbering series for the “SC Release Slip No.”. The drop-down lists all the valid numbering types that is having prefix-suffix combination in the “SCRS” OU for the transaction type “SC Release Slip” and “SCRS” along with blank option

SC Release Slip Date

The creation date of the subcontract release slip (Date Format). Mandatory The system date is displayed by default.

Note: if “SC release slip Date” is blank then system date is taken as the default “SC release slip Date”

The “SC release slip Date” should not be greater the “System Date

Folder

Use the drop-down list box to select the classification of the subcontract order document. The drop-down lists the user-defined values for the “SCRS Folder” from the Type Setup Component

Buyer

Use the drop-down list box to select the buyer of the subcontracted items.  The drop-down lists all the valid buyer code for the login ID entered which are active and effective on the SCRS date along with the “Blank” option. Capturing the Buyer depends on the System Parameter value (‘Buyer Control Mandatory’ set as ‘YES’ or ‘NO’) ; if a Buyer is specified in a SCRS, then the items ordered are checked for the validity of the Buyer.

The system displays the following information “SC Release Slip Details” group box

 BSCO No.

The unique code identifying the BSCO

Blanket SCO Date

The creation date of the blanket subcontract order (Date Format). Mandatory The system date is displayed by default.

Blanket Order Type          

Use the drop-down list box to select the type of subcontract. The possible values are Service, Activity and Conversion

Supplier Code

The unique identifying the supplier

Name

The name of the supplier

Contract Type

The type of Contract. The possible values are Rate, Quantity and Value

BSCO Created At

The OU where the BSCO was created

BOM Modifiable in SC Rel Slip No

Indicates whether the Bill of Materials associated with the line items of the BSCO is modifiable or not

Rate Control

Displays whether control on rate is needed for the period of blanket subcontract order

Remarks

Remarks if any, pertaining to the subcontract release slip (Alphanumeric, 256)

Hold

Select/Deselect to put the SC release slip in to the hold status. A held SC Release slip cannot be approved. A document is put into the “held” status when certain uncertainty exists with the document

Contact Person

The contact person in the organization (Alphanumeric, 45)

Approval Date

The date on which the subcontract release slip is approved for further processing  (Date Format)

The system displays the following information in the “SC Release Slip Amount Details” group box

SC Release Slip Amount

The total value of the SC Release Slip. This sum of the values of the all the items in the SC Release Slip. This is displayed when the “Create” or “Create and Approve” pushbutton is pressed

Additional Charges

Additional charges incurred on the SC Release Slip. This is sum of all the line level TCDs and document level TCD.

Total value

The total value of the SC Release Slip. This is sum of “SC Release Slip Value” and “Additional Charges”. This is displayed when the “Create” or “Create and Approve” pushbutton is pressed

Currency

The transaction currency of the SC Release Slip.

Exchange Rate

The exchange rate of the currency selected in the “Currency” drop-down list against the base currency of the financial company to which the “SCRS” OU is associated. The default value is set as “1”. This cannot be blank

Note: The “Exchange Rate” is displayed when the currency is selected in the “Currency” drop-down which can be modified

The system displays the following fields on the “SCO Amount Details” group box

Base Currency Value

The base currency of the financial company to which the “SCRS” OU is associated

Budget ID

Unique identifier for a particular Budget associated with the purchase of the Line Item. (Alphanumeric, 6).

 

Help facility available

Need Date

The date on which the items needs to be received (Date Format)

CC Usage

Use the drop-down box to select the cost center usage (consumption Point) for the item. The drop-down lists all the CC usages defined for the “Purchase Cost Center” in the “Cost Rule Definition” component. The CC usage is specified whenever an item is moved to a Cost Center instead of a warehouse Example::  Service Item/ Adhoc Item.. “Blank” is set as the default value. This cannot be “Blank” if “Adhoc Item Class” has any value other than “None”.

Receipt At

Use drop down box to select the OU in which the Items are to be received from the Supplier. The drop-down lists active “GR OU” that are mapped to the “SCRS” component that also belongs to the same financial company and the business unit as the SCRS OU

Warehouse Code

The code identifying the warehouse where the item needs to be stored (Alphanumeric, 10). The warehouse entered must be defined in any of the GR OUS mapped to the “SCRS” component if the code is in “Active” status

 

Help facility available

BSCO Line No.

The unique number identifying the line number of the item in the BSCO

 

Press <Enter> Key

 

Help facility available

The system displays the following in the “SC Item Details” Multiline

Item Code

The unique code identifying the item to be subcontracted

Variant Code

The variant of the item to be subcontracted

Description

The textual description of the item

BSCO Balance Quantity

The quantity of items which has not be delivered as per the BSCO

Quantity

The number of units to be subcontracted (Integer). The value should not be negative or zero.

The system displays the following in the “SC Item Details” Multiline

UOM

The unit of measurement of the items supplied by the supplier.

Cost

The cost of the number of units specified in the “Per” field (Integer) . The cost cannot be blank for given if “Item”/“Variant” or “Description” is specified. Cost should be a positive number

 

Press <Enter> Key

Per

The number of units for which the cost is applied (Integer)

Budget ID

Unique identifier for a particular Budget associated with the purchase of the Line Item. (Alphanumeric, 6)

 

Press <Enter> Key

 

Help facility available

 The system displays the following information “SC Item Details” multiline

BOM Reqd.

Use the drop down box and select  “Yes” if Billing of material is required else select “no”

BOM Reference

The unique code identifying the Billing of Materials for the item to be subcontracted. The “BOM Reference” cannot be blank if “BOM Reqd” is “Yes”

 

Press <Enter> Key

 

Help facility available

Receipt At

Use drop down box to select the OU in which the Items are to be received from the Supplier. The drop-down lists active “GR OU” that are mapped to the “SCRS” component that also belongs to the same financial company and the business unit as the SCRS OU

Warehouse Code

The code identifying the warehouse where the item needs to be stored (Alphanumeric, 10). The warehouse entered must be defined in any of the GR OUS mapped to the “SCRS” component if the code is in “Active” status

 

Help facility available

Schedule Type

Use the drop-down list box to select the schedule type of the item in the BSCO

 
  • Single – If all the items needs to delivered in the batch on the same date

 
  • Staggered – If the items can be segregated into various batches and can be delivered on different dates

Need Date

The date on which the items needs to be delivered (Date Format)

Accounting Unit

Use the drop-down list box to select the accounting unit to which the values are posted. Displays all the active finance books associated to the “SCRS” organization unit. The drop-down also displays “Blank” option. The “Accounting Unit” cannot be blank for a line item. If  “Accounting unit is left blank and if only one accounting unit is associated with “SCRS” organization unit then that accounting unit is set as the default value for the “Accounting Unit”.

Ref Doc Type

Use the drop-down list box to select the type of the reference document. None is displayed by default

 
  • None – Indicates the BSCO does not refer to any document fs

 
  • Production WO – Indicates that the reference document is a production work order

 
  • Maintenance WO - Indicates that the reference document is a maintenance work order

 
  • Maintenance Plan - Indicates that the reference document is a maintenance plan

Ref Doc No

The unique code identifying the reference document. (Alphanumeric, 20)

Ref Doc Line no

The line number of the item in the reference document to which the line item in the subcontract order refers  (Integer)

The system displays the following information “SC Item Details”

Drawing Revision No

The unique engineering drawing revision number of the item given within a budget identification number

Basic Value

The basic value of the line item

 

Basic Value = Cost /Per * Quantity

Total Value

This value is displayed when the “Create Blanket SCO” or “Approve Blanket SCO” pushbutton is pressed. This is the sum of the basic value of the line item and the TCD amount to be included in the cost of the line item.

 

Total value = Basic Value (Line item) + TCD Value (add to stock)

Adhoc Item Class

The item class of the non-codified item

Rate Tolerance +ve

The acceptable percentage of increase in the price of item.

Remarks

Remarks if any, pertaining to the item in the BSCO

Note: Atleast one item code-variant combination or Item description has to be entered in the Multiline.

If all the mandatory information has been entered and validated the status of the subcontract release slip is set to "Fresh" upon creation of the document

If all the mandatory information has been entered and validated the status of the subcontract release slip is set to "Open" upon creation of the document

An auto invoice is generated for the total value of those line items with two-way matching type and if auto invoicing is set to “Yes”

The system displays the following fields:

Created By

The login ID of the person who created the subcontract release slip

Created Date

The date on which the subcontract release slip

To proceed, carry out the following

Top

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Create SC Release Slip - An Overview

Activity Overview

This page displays all the Blanket Subcontract Order (BSCO) details like the unique code identifying the BSCO, type of BSCO, date on which the BSCO was raised, supplier details, BSCO basic value and balance value

You can enter the unique code identifying the SCRS, the date on which the SCRS is raised, the buyer who is identified for the procurement of the item, the unique code identifying the budget which is updated by the procurement of the items, the date on which the items needs to be delivered, the warehouse where the items are stored, the cost center which is affected by the transaction, the OU where a receipt for the received goods is made.

Top