This page allows you to create an SCRS based on the selected BSCO. Tell me more
Select the “Create SC Release Slip” link from the “Select Blanket Subcontract Order” page
The “Create SC Release Slip” page appears
The system displays the following in the header
|
Status |
The status of the SCRS |
Enter the following fields in the “SC Release Slip Details”
|
SC Release Slip No. |
The unique code identifying the subcontract release slip. (Alphanumeric, 18) Mandatory. This number is automatically generated and displayed by The system at the time of creating the, based on the numbering type selected in this page. The number should be entered if the “Numbering series” is “Manual” |
Note: The “Blanket SCO NO” should not be blank if the “Numbering Series” is set to “Manual”
The “SC Release Slip No.” is auto generated if the “Numbering Series” is anything other than “Manual” with the prefix or suffix selected in the “Numbering Series” on the click of “Create” or “Create and Approve” pushbutton
The system displays the following information “SC Release Slip Details” group box
|
Amendment No. |
A unique code identifying the amendment done to the subcontract release slip. Amendment is normally done after the approval of the document |
Enter the following fields in the “SC Release Slip Details”
|
Numbering Series |
Use the drop-down list box to select the numbering series for the “SC Release Slip No.”. The drop-down lists all the valid numbering types that is having prefix-suffix combination in the “SCRS” OU for the transaction type “SC Release Slip” and “SCRS” along with blank option |
|
SC Release Slip Date |
The creation date of the subcontract release slip (Date Format). Mandatory The system date is displayed by default. |
Note: if “SC release slip Date” is blank then system date is taken as the default “SC release slip Date”
The “SC release slip Date” should not be greater the “System Date
|
Folder |
Use the drop-down list box to select the classification of the subcontract order document. The drop-down lists the user-defined values for the “SCRS Folder” from the Type Setup Component |
|
Buyer |
Use the drop-down list box to select the buyer of the subcontracted items. The drop-down lists all the valid buyer code for the login ID entered which are active and effective on the SCRS date along with the “Blank” option. Capturing the Buyer depends on the System Parameter value (‘Buyer Control Mandatory’ set as ‘YES’ or ‘NO’) ; if a Buyer is specified in a SCRS, then the items ordered are checked for the validity of the Buyer. |
The system displays the following information “SC Release Slip Details” group box
|
BSCO No. |
The unique code identifying the BSCO |
|
Blanket SCO Date |
The creation date of the blanket subcontract order (Date Format). Mandatory The system date is displayed by default. |
|
Blanket Order Type |
Use the drop-down list box to select the type of subcontract. The possible values are Service, Activity and Conversion |
|
Supplier Code |
The unique identifying the supplier |
|
Name |
The name of the supplier |
|
Contract Type |
The type of Contract. The possible values are Rate, Quantity and Value |
|
BSCO Created At |
The OU where the BSCO was created |
|
BOM Modifiable in SC Rel Slip No |
Indicates whether the Bill of Materials associated with the line items of the BSCO is modifiable or not |
|
Rate Control |
Displays whether control on rate is needed for the period of blanket subcontract order |
Enter the following fields in the “SC Release Slip Details” group box
|
Remarks |
Remarks if any, pertaining to the subcontract release slip (Alphanumeric, 256) |
|
Hold |
Select/Deselect to put the SC release slip in to the hold status. A held SC Release slip cannot be approved. A document is put into the “held” status when certain uncertainty exists with the document |
|
Contact Person |
The contact person in the organization (Alphanumeric, 45) |
|
Approval Date |
The date on which the subcontract release slip is approved for further processing (Date Format) |
The system displays the following information in the “SC Release Slip Amount Details” group box
|
SC Release Slip Amount |
The total value of the SC Release Slip. This sum of the values of the all the items in the SC Release Slip. This is displayed when the “Create” or “Create and Approve” pushbutton is pressed |
|
Additional Charges |
Additional charges incurred on the SC Release Slip. This is sum of all the line level TCDs and document level TCD. |
|
Total value |
The total value of the SC Release Slip. This is sum of “SC Release Slip Value” and “Additional Charges”. This is displayed when the “Create” or “Create and Approve” pushbutton is pressed |
|
Currency |
The transaction currency of the SC Release Slip. |
Modify the following fields in the “Amount Details” group box
|
Exchange Rate |
The exchange rate of the currency selected in the “Currency” drop-down list against the base currency of the financial company to which the “SCRS” OU is associated. The default value is set as “1”. This cannot be blank |
Note: The “Exchange Rate” is displayed when the currency is selected in the “Currency” drop-down which can be modified
The system displays the following fields on the “SCO Amount Details” group box
|
Base Currency Value |
The base currency of the financial company to which the “SCRS” OU is associated |
Enter the following fields in the “Default Entries” group box.
|
Budget ID |
Unique identifier for a particular Budget associated with the purchase of the Line Item. (Alphanumeric, 6). |
|
Help facility available |
|
|
Need Date |
The date on which the items needs to be received (Date Format) |
|
CC Usage |
Use the drop-down box to select the cost center usage (consumption Point) for the item. The drop-down lists all the CC usages defined for the “Purchase Cost Center” in the “Cost Rule Definition” component. The CC usage is specified whenever an item is moved to a Cost Center instead of a warehouse Example:: Service Item/ Adhoc Item.. “Blank” is set as the default value. This cannot be “Blank” if “Adhoc Item Class” has any value other than “None”. |
|
Receipt At |
Use drop down box to select the OU in which the Items are to be received from the Supplier. The drop-down lists active “GR OU” that are mapped to the “SCRS” component that also belongs to the same financial company and the business unit as the SCRS OU |
|
Warehouse Code |
The code identifying the warehouse where the item needs to be stored (Alphanumeric, 10). The warehouse entered must be defined in any of the GR OUS mapped to the “SCRS” component if the code is in “Active” status |
|
Help facility available |
Click the “Default” pushbutton to display the values entered in the “Default Entries” group box in the corresponding fields in the “SC Item Details” multiline
Modify the following fields in the “SC Item Details” multiline if required:
|
BSCO Line No. |
The unique number identifying the line number of the item in the BSCO |
|
Press <Enter> Key |
|
|
Help facility available |
The system displays the following in the “SC Item Details” Multiline
|
Item Code |
The unique code identifying the item to be subcontracted |
|
Variant Code |
The variant of the item to be subcontracted |
|
Description |
The textual description of the item |
|
BSCO Balance Quantity |
The quantity of items which has not be delivered as per the BSCO |
Modify the following fields in the “SC Item Details” multiline if required:
|
Quantity |
The number of units to be subcontracted (Integer). The value should not be negative or zero. |
The system displays the following in the “SC Item Details” Multiline
|
UOM |
The unit of measurement of the items supplied by the supplier. |
Modify the following fields in the “SC Item Details” multiline if required:
|
Cost |
The cost of the number of units specified in the “Per” field (Integer) . The cost cannot be blank for given if “Item”/“Variant” or “Description” is specified. Cost should be a positive number |
|
Press <Enter> Key |
|
|
Per |
The number of units for which the cost is applied (Integer) |
|
Budget ID |
Unique identifier for a particular Budget associated with the purchase of the Line Item. (Alphanumeric, 6) |
|
Press <Enter> Key |
|
|
Help facility available |
The system displays the following information “SC Item Details” multiline
|
BOM Reqd. |
Use the drop down box and select “Yes” if Billing of material is required else select “no” |
Modify the following fields in the “SC Item Details” multiline if required:
|
BOM Reference |
The unique code identifying the Billing of Materials for the item to be subcontracted. The “BOM Reference” cannot be blank if “BOM Reqd” is “Yes” |
|
Press <Enter> Key |
|
|
Help facility available |
|
|
Receipt At |
Use drop down box to select the OU in which the Items are to be received from the Supplier. The drop-down lists active “GR OU” that are mapped to the “SCRS” component that also belongs to the same financial company and the business unit as the SCRS OU |
|
Warehouse Code |
The code identifying the warehouse where the item needs to be stored (Alphanumeric, 10). The warehouse entered must be defined in any of the GR OUS mapped to the “SCRS” component if the code is in “Active” status |
|
Help facility available |
|
|
Schedule Type |
Use the drop-down list box to select the schedule type of the item in the BSCO |
|
|
|
|
|
Need Date |
The date on which the items needs to be delivered (Date Format) |
|
Accounting Unit |
Use the drop-down list box to select the accounting unit to which the values are posted. Displays all the active finance books associated to the “SCRS” organization unit. The drop-down also displays “Blank” option. The “Accounting Unit” cannot be blank for a line item. If “Accounting unit is left blank and if only one accounting unit is associated with “SCRS” organization unit then that accounting unit is set as the default value for the “Accounting Unit”. |
|
Ref Doc Type |
Use the drop-down list box to select the type of the reference document. None is displayed by default |
|
|
|
|
|
|
|
|
|
Ref Doc No |
The unique code identifying the reference document. (Alphanumeric, 20) |
|
Ref Doc Line no |
The line number of the item in the reference document to which the line item in the subcontract order refers (Integer) |
The system displays the following information “SC Item Details”
|
Drawing Revision No |
The unique engineering drawing revision number of the item given within a budget identification number |
|
Basic Value |
The basic value of the line item |
|
Basic Value = Cost /Per * Quantity |
|
|
Total Value |
This value is displayed when the “Create Blanket SCO” or “Approve Blanket SCO” pushbutton is pressed. This is the sum of the basic value of the line item and the TCD amount to be included in the cost of the line item. |
|
Total value = Basic Value (Line item) + TCD Value (add to stock) |
|
|
Adhoc Item Class |
The item class of the non-codified item |
|
Rate Tolerance +ve |
The acceptable percentage of increase in the price of item. |
Modify the following fields in the “SC Item Details” multiline if required:
|
Remarks |
Remarks if any, pertaining to the item in the BSCO |
Note: Atleast one item code-variant combination or Item description has to be entered in the Multiline.
Check the checkbox in the multiline to select the items to be saved to the BSCO
Click the “Create SC Release Slip” pushbutton to create subcontract release slip
If all the mandatory information has been entered and validated the status of the subcontract release slip is set to "Fresh" upon creation of the document
Click the “Create and Approve SC Release Slip” pushbutton to create subcontract release slip
If all the mandatory information has been entered and validated the status of the subcontract release slip is set to "Open" upon creation of the document
An auto invoice is generated for the total value of those line items with two-way matching type and if auto invoicing is set to “Yes”
The system displays the following fields:
|
Created By |
The login ID of the person who created the subcontract release slip |
|
Created Date |
The date on which the subcontract release slip |
To proceed, carry out the following
Select the “View Item Details” link at the bottom of the page to view the details of the item selected in the multiline
Select the “View BOM Details” link at the bottom of the page to view the Bill Of Material Details
Select the “View Warehouse Details” link at the bottom of the page to view the Warehouse details
Select the “View Budget Details” link at the bottom of the page to view the budget details.
Select the “View Buyer Details” link at the bottom of the page to view the buyer details
Select the “Specify Receipt List” at the bottom of the page to specify the list of items to be received from the supplier
Select the “Specify Issue List” at the bottom of the page to specify the list of items to be issued to the supplier
Select the “Specify Inclusion/Exclusion List” at the bottom of the page to specify the items that are included and excluded for issue for the line items in the subcontract release slip
Select the “Specify Schedule and Distribution” at the bottom of the page to specify schedule and distribution details for the items in the subcontract release slip
Select the “Specify Terms & Condition” at the bottom of the page to specify the terms and condition pertaining to the subcontract release slip
Select the “Specify TCD Details” at the bottom of the page to specify the tax, charges and discount applicable on the line items and entire document of subcontract release slip
Select the “Tax Calculation - Summary” at the bottom of the page to specify the tax details for subcontract release slip
Select the “Specify Quality Attributes” at the bottom of the page to specify quality specification for the line items in the subcontract release slip
Select the “Specify SC Release Slip-SCR Coverage” at the bottom of the page to specify the coverage done by the subcontract release slip against the subcontract request,
Select the “Attach Notes” at the bottom of the page to attach additional information to the subcontract release slip
Select the “Edit SC Release Slip” at the bottom of the page to modify an existing subcontract release slip
Select the “View Earliest Available Date Details” link at the bottom of the page to view the earliest date when the items will be available
Select the “View Disposition Review Details” link at the bottom of the page to view the Disposition details pertaining to the line items
Select the “View Free Stock Review Details” link at the bottom of the page to free stock review details
Select the “View Stock Status Details” link at the bottom of the page to view the status of the stock
Select the “View Warehouse Stock Status Details” link at the bottom of the page to view the status of the stock in the warehouse
Select the “Supplier” at the bottom of the page to view the supplier details of the subcontract release slip
Select the “Warehouse” at the bottom of the page to view the warehouse details of the tem selected in the multiline.
Select the "Operational Checklist" link to record the check list required for the subcontract release slip.
Create SC Release Slip - An Overview
This page displays all the Blanket Subcontract Order (BSCO) details like the unique code identifying the BSCO, type of BSCO, date on which the BSCO was raised, supplier details, BSCO basic value and balance value
You can enter the unique code identifying the SCRS, the date on which the SCRS is raised, the buyer who is identified for the procurement of the item, the unique code identifying the budget which is updated by the procurement of the items, the date on which the items needs to be delivered, the warehouse where the items are stored, the cost center which is affected by the transaction, the OU where a receipt for the received goods is made.